CONTRIBUTIONS OF THE
RESTRUCTURING OF THE
ELECTRIC POWER INDUSTRY TO
THE
AUGUST 14, 2003 BLACKOUT
By Jack Casazza
Frank Delea
George Loehr
Members, Power Engineers Supporting Truth
August 2005
IV. Change in
Industry Structure
V. Lessons Learned from the Analyses of
the August 2003 Blackout
VI. Change in Focus from Coordination
to Competition.
A. Prior
Coordination Procedures
B. Changes
Caused by Restructuring
VII.
Expenditure Reductions to Improve Profits
A. Reductions
in Transmission Additions and Maintenance
IX. Failure to Pass on Past Knowledge
A. Investigations
of Past Blackouts
B. Investigation
of August 14, Blackout
This report addresses whether the
restructuring of the electric utility industry in the United States, and most specifically
in the Midwest Independent System Operator (MISO) area, contributed to the
August 2003 blackout in northeastern North America.
There have been numerous
after-the-fact reviews of the August 2003 blackout. The various institutional
reports by the Department of Energy (DOE), North American Electric Reliability
Council (NERC), East Central Area Reliability Coordination Agreement (ECAR),
etc., addressed the cause of the blackout by looking one step beyond the most
immediate causes. As noted in Chapter
3, page 17 of the April 2004 Final Report of the U.S. Canada Power System
Outage Task Force:
“A dictionary definition of “cause” is “something that
produces an effect, result, or consequence.”1 In searching for the
causes of the blackout, the investigation team looked back through the
progression of sequential events, actions and inactions to identify the
cause(s) of each event. The idea of “cause” is here linked not just to what
happened or why it happened, but more specifically to the entities whose duties
and responsibilities were to anticipate and prepare to deal with the things
that could go wrong. Four major causes, or groups of causes, are identified
(see box on page 18).
Although the causes discussed below produced the failures
and events of August 14, they did not leap into being that day. Instead, as the
following chapters explain, they reflect long-standing institutional failures
and weaknesses that need to be understood and corrected in order to maintain
reliability.”
Although this quote suggests that
the investigation focused on underlying causes of the blackout, the
post-blackout reviews did not specifically address the true root causes, as
illustrated by the following extracts from two ECAR reports.
“ECAR
INVESTIGATION OF AUGUST 14, 2003 BLACKOUT by MAJOR SYSTEM DISTURBANCE ANALYSIS
TASK FORCE
Technical Report”
“It should be noted that the pursuit of the root causes to
the above factors was not within the scope of this MSDATF effort, and hence,
root causes are not addressed in the [Major System Disturbance Analysis Task
Force] MSDATF Technical Report.”
“ECAR
INVESTIGATION OF AUGUST 14, 2003 BLACKOUT by MAJOR SYSTEM DISTURBANCE ANALYSIS
TASK FORCE
Recommendations Report”
“The technical analysis of what happened in ECAR was done
by the ECAR Major System Disturbance Analysis Task Force (MSDATF), which
focused specifically on the system behavior during the events leading up to and
through the blackout, on the system response to the various events, and on the
behavior of the protective relaying systems as the events progressed throughout
the afternoon of August 14.”
The post-blackout reviews
attempted to determine what happened or didn’t happen from a technical
perspective. They did not take the next
step and ask why – what managerial decisions were made, or not made,
that brought about the more immediate causes of the blackout.
For example, tree contact was
identified as an immediate cause of power line tripouts. This was explained by unacceptable
right-of-way maintenance practices. What was not pursued was why the companies involved had decided on
their right-of-way maintenance practices.
Could it have been to maximize immediate profits?
Similarly, inadequate situation
awareness has been identified as another immediate cause. This was explained, in part, by deficiencies
in the analytical capabilities of control centers, communication protocols,
training, etc. However, the reasons for
these deficiencies were not pursued.
Could the reasons have included decisions to keep costs down so as to
show better financial results? Could
there have been a decision to “speed things up” when establishing MISO, in
reaction to external pressures to establish a new market structure, before all
physical and management systems were in place?
Unfortunately, the information
required to answer these broader questions is not publicly available and these
questions have not even been asked, nor have secondary sources of information
(e.g., maintenance expenditures as found in required company submissions to the
Federal Energy Regulatory Commission (FERC)) been reviewed.
This
report attempts to lay out some of the pertinent questions that are still
unanswered and, where possible, supply relevant information and conclusions
related to these questions.
The review
presented in this report was conducted by a group of engineers with extensive
high-level experience in the electric power industry and access to information
from several hundred individuals involved in the industry. While it was triggered by the August 14,
2003 blackout, it has necessarily involved a more general concern with how
national policies have affected the reliability of electricity service to
American consumers. It considers the
roles of industry and government, particularly FERC. It focuses on reliability, examines the responsibilities and
failures of NERC, includes brief discussions of the government’s investigation
of the August 14, 2003 blackout, and calls attention to some as-yet unanswered
questions. It is based on two essential
ingredients:
Ø
When comparing
alternatives, characterize
them correctly. In reviewing the effect
of deregulation on the August 14th blackout, it is essential that comparisons be made based
on accurate information about prior procedures. Unfortunately, many who make such comparisons often have very
little knowledge of past procedures.
Ø
Avoid being influenced by
political, commercial, or personal power concerns. The most precious thing that anyone can bring to a review of
policy, such as this report, is to be an honest witness to what he or she
knows.
Deregulation and the concomitant
restructuring of the electric power industry in the U.S. have had a devastating
effect on the reliability of North American power systems, and constitute the
ultimate root cause of the August 14, 2003 blackout. Specifically, deregulation and restructuring have led to:
Ø
Changes in focus from
long-term optimization and inter-system coordination and reliability to total
dependence on immediate profits and the efficacy of “the market.”
Ø
Change in technical
qualifications of those holding management positions in electric power
organizations and government policy makers and regulators; this change affects
entire organizations.
Ø
Reductions in personnel at
electric power organizations and companies.
Ø
Failure to make adequate
technical analyses including risks when setting government policies.
Ø
Increased complexity of
operations because of separation of generation and transmission functions, the
large increase in the number of organizations involved, and the establishment
of additional levels of responsibility in the operation/control process.
Ø
Dilution of management
responsibility, including too many entities in the management structure with veto power.
Ø
An almost fundamentalist
reliance on markets to solve even the most scientifically complex problems.
Ø
Decreased emphasis on the
importance of strong reliability standards, and a trend toward lower
standards; this is most pronounced in
the very organization charged with maintaining reliability –NERC – aided and
abetted by FERC.
Ø
Dispersed, fragmented control
of the bulk power system in the Midwest.
Ø
A patchwork quilt of
overlapping jurisdictions among marketing areas, Independent System Operators/Regional
Transmission Organizations (ISOs/RTOs), and regional reliability councils in
the midwest.
Ø
Reductions in, or outright
elimination of, training including training of operators.
Ø
Continuation of the
historical problem of geo-electrically small control areas in the Midwest,
despite the creation of the MISO, which, in the context of operations on August
14, 2003, appeared to be little more than a toothless shell.
Unless the root causes of the
August 14, 2003 blackout are addressed and the trend toward lower standards
reversed, the likelihood of future blackouts will increase.
The DOE/Canadian report
demonstrates the dominance of market participants and lack of government
concern about the root causes of the blackout. [1],
[2] Both are also clearly illustrated by the
almost two-year delay in the investigations, and discussions that are taking
place through the competition and reliability study of which this paper is
part.
Despite its “spin”, the Energy
Policy Act of 2005 does nothing to address the root causes of the 2003
blackout, and hence will do nothing to enhance reliability.
To understand the changes that have taken place in the structure of the electricity industry, it is necessary to compare current and prior procedures and examine the increased complexity of today’s system relative to the system of the past.
From the
installation of inter-regional transmission ties in the 1960s until the start
of restructuring/deregulation in the 1990s, generation and transmission were
planned, designed, and operated on a regionally coordinated basis.[3]
[4] Most individual power companies were
vertically integrated, so development of generation and transmission was
coordinated. Installation of generation
took into account transmission limits, and installation of transmission took
into account generation needs.
Hierarchal organizations (power pools) evolved covering multi-company
areas and each having limited numbers of participants; e.g., the Pennsylvania-New
Jersey-Maryland Interconnection (PJM), New York Power Pool (NYPP), and New
England Pool (NEPOOL). Power pools in turn combined to form
regional reliability councils; e.g., Mid-Atlantic Area Council ((MAAC),
ECAR, and Northeast Power Coordinating Council (NPCC). These councils coordinated through
organizations such as MEN (consisting of MAAC, ECAR, and NPCC), VEM (consisting
of VACAR, ECAR, and MAAC), and VAST (consisting of VACAR, American
Electric Power [AEP], Southern, and
Tennessee Valley Authority [TVA]).
Reliability criteria, monitoring and enforcement were accomplished by
the regional councils, which had boundaries congruent with planning and
operating organizations. Inter-regional
coordination was accomplished by organizations such as MEN, VEM, and VAST.
The various
organizations communicated often and effectively and cooperated both on
real-time operating basis and on a longer-term planning basis. Sales and purchases of power were conducted
through these hierarchal organizations, and each organization was well aware of
conditions in other systems that could affect it. Each system’s plans were coordinated with those of its neighbors.
However,
during the past 15 years, the structure – indeed the very underpinnings – of
the electric power industry have changed.
The following phenomena are key indicators of s the
changes in the industry’s structure:
Ø
The functional separation of
generation and transmission within companies as mandated by Order 888. Reliable planning and operation of a bulk
supply system requires full coordination between generation and transmission;
this functional separation made coordination much more difficult.[5] In most companies system planning
departments were split up or disbanded.
Typical organizational impacts were:
·
The diffusion of best
technical knowledge which in the past was centered in planning departments.
·
Severe reductions in
personnel in generation and transmission, including encouragement of senior personnel to take early
retirement. These reductions
effectively ended the transfer of essential expertise from one generation to
the next.[6],
[7],
[8],
[9],
[10]
·
Reductions in training as a
means of reducing costs.
·
The divestiture by many
private utilities of their generation resources in response to regulatory
pressures. Many companies either “spun-off” their generating assets into
unregulated affiliates or sold them to third parties. This increased number of
“players” greatly complicated the system planning process and diffused
responsibility for maintaining a reliable system.
Ø
The transfer of control of
transmission assets in response to federal regulatory requirements to
ISOs/RTOs, the majority of whose boards were made up of individuals with no
knowledge of power system operational or reliability issues.[11]
Ø
Entrance of merchant power
plants into the power system. This also
complicated the system planning process and diffused responsibility for
maintaining a reliable system.
Ø
New market areas were
established that were inconsistent with the boundaries of responsible operating
entities and/or the regional councils responsible for reliability standards and
enforcement. For example, the PJM and
PJM West marketing area stretches across three reliability councils, at least
three ISO/RTO-type organizations, and numerous control areas.
Ø
An increase in system and
decision making complexity, with more opportunities for delay and the
likelihood of “watering down” decisions to the lowest common denominator. On the day of the August 14, 2003 blackout,
MISO had neither the authority nor technical means to operate a generation and
transmission grid in the region. Since
formal spot-markets had not been established, a large number of bi-lateral
contract trades originated with IPPs, complicating system operations[12].
These IPPs had little incentive to provide needed reactive power on the day of
the blackout.
The changes
described above have created a more complicated and compartmentalized industry
structure than was the case in the past.
One example of the increased complication is the extraordinary increase
in the membership of three “old line” power pools. The New York Independent System Operator (NYISO) 2004 Annual Report[13]
cites 245
“market participants” significantly more than the eight members that made up
NYPP prior to restructuring. Each of
these 245 “market participants”
can make decisions about buying and selling electric power that affect the
transmission system in New York and in other regions. In 1993, PJM had 10 members and served 23 million people in five
states and the District of Columbia [14]. Today, PJM has
more than 350 members and operates in 13 states and the District of Columbia. ISO New England now
has 237 market organizations, 150 of which are members of the Participants’
Committee[15]. The complexity of the decision-making
process has increased on the same scale in other regions of the country. There have not been significant changes
since the 2003 Bblackout.
In addition
to an absolute increase in the number of participants, the inter-relationships
between and among the participants have changed. No longer are decisions made by a relatively small number of
non-competing organizations; today, decisions are made by a large number of
entities, most of which are competitors and each of which has more interest in
profit than in bulk-power-system reliability.
Procedural rules established between and among the various parties are
no longer matters of overall corporate policy, but rather of contractual
arrangements based on the parties’ financial self-interest.
In sum, the
complexity of planning and operating the electric power system has
significantly increased with the growth in the number of participants whose
decisions affect the overall system. It
has further increased because the objective of many of these organizations is
short-term profits rather than long-term reliability.[16]
For an overview of lessons learned from analysis of the 2003 blackout, we examine reviews of major blackouts in the past as well as the reports by DOE and NERC on the 2003 blackout.
Following the August 14, 2003
blackout, a number of reviews were conducted, the most visible of which was by
DOE and the Canadian government.
Separate reports were prepared by NERC; by ECAR, MAAC, and NPCC; by the
NY, New England and PJM ISOs; and by state regulatory commissions. Many of these documents focused narrowly on
technical issues. However, the DOE/Canadian and NERC
reports raise issues that could and should have been explored more deeply to
determine how the complicated organizational structure of the current
“deregulated” industry, with its heightened focus on commercial concerns, might
have contributed to the problems that led to the blackout. Our approach is to highlight some of
the conclusions/recommendations of these reports and to raise follow-up
questions that have not been addressed.
The following italicized material[17]
is excerpted from the Final Report on the
August 14, 2003 Blackout in the United States and Canada - Causes and
Recommendations - April 2004. The
inserted questions are raised by the authors of this report.
Chapter 3, “Causes of the Blackout and Violations of NERC
Standards.”
Page 19. “Group 2: Inadequate situational awareness at
FirstEnergy. FE did not recognize or understand the deteriorating condition of
its system.
Violations (Identified by NERC):
Other Problems:
In the
aggregate, the above problems raise the question of why adequate equipment,
information and training were not provided.
Page 20. “Group 4: Failure of the interconnected grid’s
reliability organizations to provide effective diagnostic support.
Violations (Identified by NERC):
Why weren’t real time data used? Was there consideration given to its use and, if so, why was the
decision made not to use it?
·
“Violation 6: PJM and MISO as reliability coordinators
lacked procedures or guidelines between their respective organizations
regarding the coordination of actions to address an operating security limit
violation observed by one of them in the other’s area due to a contingency near
their common boundary, as required by Policy 9, Appendix C. Note: Policy
9 lacks specifics on what constitutes coordinated procedures and training. “
When MISO was established and approved, why wasn’t this
most basic function of an ISO in place?
“Other Problems:
·
MISO did not have adequate monitoring capability to fulfill
its reliability coordinator responsibilities as required by NERC Policy 9,
Appendix D, Section A. “
Again, when MISO was established and approved, why wasn’t
this basic function of an ISO in place?
·
“American Electric Power (AEP) and PJM attempted to use the
transmission loading relief (TLR) process to address transmission power flows
without recognizing that a TLR would not solve the problem. “
What instructions/directions were given to the operators
when trade-offs between reliability and commerce occurred?
Page 21. “Institutional Issues
2. NERC and the
industry’s reliability community were aware of the lack of specificity and
detailing some standards, including definitions of Operating Security Limits,
definition of planned outages, and delegation of Reliability Coordinator
functions to control areas, but they moved slowly to address these problems
effectively. “
What impediments does the new stakeholder process place in
the path of the “industry’s reliability community when
it tries to move
effectively and expeditiously?
NERC in its report “August 14, 2003 Blackout: NERC Actions to
Prevent and Mitigate the Impacts of Future Cascading Blackouts – February 10,
2004” approved 14 recommendations for corrective action. Included are the
following directives to MISO:
“B. Corrective Actions to Be Completed by MISO
MISO shall complete the following corrective actions no
later than June 30, 2004.
1. Reliability Tools. MISO shall fully implement and test its
topology processor to provide its operating personnel real-time view of the
system status for all transmission lines operating and all generating units
within its system, and all critical transmission lines and generating units in
neighboring systems. Alarms should be provided for operators for all critical
transmission line outages. MISO shall establish a means of exchanging outage
information with its members and neighboring systems such that the MISO state
estimation has accurate and timely information to perform as designed. MISO
shall fully implement and test its state estimation and real-time contingency
analysis tools to ensure they can operate reliably no less than every ten
minutes. MISO shall provide backup capability for all functions critical to
reliability.
2. Visualization Tools. MISO shall provide its operating personnel
tools to quickly visualize system status and failures of key lines, generators
or equipment. The visualization shall include a high level voltage profile of
the systems at least within the MISO footprint.
3. Training. Prior to June 30, 2004 MISO shall meet the
operator training criteria stated in NERC Recommendation 6.
4. Communications. MISO shall reevaluate and improve its
communications protocols and procedures with operational support personnel
within MISO, its operating members, and its neighboring control areas and
reliability coordinators.
5. Operating Agreements. MISO shall
reevaluate its operating agreements with member entities to verify its
authority to address operating issues, including voltage and reactive
management, voltage scheduling, the deployment and redispatch of real and
reactive reserves for emergency response, and the authority to direct actions
during system emergencies, including shedding load.”
Collectively, these directives
raise the question of why approval was given by FERC for MISO to become
“operational” in the first place if so many basic operational issues have not
been resolved.
The following italicized text was excerpted from NERC’s “Technical Analysis of the August 14, 2003,
Blackout: What Happened, Why, and What Did we Learn? – Report to the NERC Board
of Trustees by the NERC Steering Group July 13, 2004”.
The first page of the July NERC report states that “… the NERC investigation did not address
regulatory, economic, market structure or policy issues” related to the
blackout. However, on pages 94 and 95 under the section titled “Causal Analysis
Results”, a tantalizing statement is made that reinforces our view that
additional investigation is warranted (emphasis added).
“The causes of the blackout described here did not result
from inanimate events, such as ‘the alarm processor failed’ or ‘a tree
contacted a power line.’ Rather, the
causes of the blackout were rooted in deficiencies resulting from decisions,
actions, and the failure to act of the individuals, groups, and organizations
involved. These causes were preventable prior to August 14 and are correctable.
Simply put — blaming a tree for contacting a line serves no useful purpose. The
responsibility lies with the organizations and persons charged with
establishing and implementing an effective vegetation management program to
maintain safe clearances between vegetation and energized conductors.
“Each cause identified here was verified to
have existed on August 14 prior to the blackout. Each cause was also determined
to be both a necessary condition to the blackout occurring and, in conjunction
with the other causes, sufficient to cause the blackout. In other words, each
cause was a direct link in the causal chain leading to the blackout and the
absence of any one of these causes could have broken that chain and prevented the
blackout. This definition distinguishes causes as a subset of a broader
category of identified deficiencies. Other deficiencies are noted in the next
section; they may have been contributing factors leading to the blackout or may
present serious reliability concerns completely unrelated to the blackout, but
they were not deemed by the investigators to be direct causes of the blackout.
They are still important; however, because they might have caused a blackout
under a different set of circumstances.”
The following italicized sections are some of the General
Conclusions also from page 94 of the NERC report. The questions inserted between the quoted texts are those that we
believe need to be addressed.
• Reliability and control areas have adopted differing
interpretations of the functions, responsibilities, authorities, and
capabilities needed to operate a reliable power system.”
The reliability coordinator function is relatively new
(post restructuring). Why was it approved with such apparent weaknesses in its
mission?
“• Deficiencies identified in studies of prior large-scale blackouts were
repeated, including deficiencies in vegetation management, operator training,
and tools to help operators better visualize system conditions. “
What are the reasons for the inattention to these prior problems?
The following quotations come from page 101 of the NERC report, in
the section entitled “Summary of Other Deficiencies in the Blackout
Investigation”:
“22. Operating entities and reliability coordinators demonstrated
an over-reliance on the administrative levels of the [transmission loading
relief] TLR procedure to remove contingency and actual overloads, when
emergency redispatch of other emergency actions were necessary. TLR is a market based congestion relief
procedure and is not intended for removing an actual violation in real time.”
This observation raises the question of what managerial
directions/guidance/instructions operators had been given vis-à-vis the
relative importance of reliability and the market.
“NERC’s technical analysis of the August 14 blackout leads
it to fully concur with the Task Force Interim Report regarding the direct
causes of the blackout. The report stated that the principal causes of the
blackout were that FE did not maintain situational awareness of conditions on
its power system and did not adequately manage tree growth in its transmission
rights-of-way. Contributing factors included ineffective diagnostic support
provided by MISO as the reliability coordinator for FE and ineffective
communications between MISO and PJM.”
Why was MISO authorized by FERC if MISO was unable to
provide effective diagnostic support, or if there were ineffective
communications capabilities between MISO and PJM?
The remaining sections of this report attempt, to the extent
feasible, to answer the
questions raised above and to explain how restructuring caused the blackout, as
well as an overall national decline in the reliability of electric power
systems.
To understand how industry restructuring has led to a change in focus from coordination to competition, we summarize the coordination procedures of the past (regulated) industry and the changes that have resulted from deregulation.
Electric
power systems require investments in major facilities typically costing from
tens of millions to billions of dollars.
These facilities have long lead times, requiring many years from start
to completion, and often remain in service for up to 40 years. Regulation provided for the return of
the investment (depreciation) and the return on the investment
(earnings) over the facilities’ lifetimes.
Electricity
systems were interconnected to take advantage of diversity in times of peak
use, equipment outages and emergencies.
The industry’s focus was on reliability and long-term cost
minimization. In that environment, a
high degree of cooperation developed among those involved in owning, managing,
planning, and operating electric power systems.[18] This level of coordination and cooperation
was accelerated in the years following the November 9, 1965 blackout.
With
deregulation and restructuring, the emphasis shifted from technical knowledge
and competence to financial and marketing knowledge. Economic theory replaced engineering fact. The new managers are driven by the desire
for “immediate profit.” This has
sometimes led to conflicts between marketers focused on profits and system
operators responsible for reliability, and disputes have been arbitrated by top
management.[19]
In brief,
restructuring fostered policies that involved increased reliability risk taking
in order to improve profits.
Deregulation has resulted in reductions in expenditures on transmission facilities, maintenance, and personnel in the industry.
There has
been a 25 percent reduction in expenses for maintenance of power-system
facilities[20] (including
but not limited to tree trimming), and in personnel, (including
operating personnel). In many companies, the time between routine
maintenance schedules has more than doubled since deregulation.[21] Between 1990 and 2000,
transmission investment fell at a rate of about $50 million a year.[22]
The labor
force at investor-owned utilities decreased from 480,000 to 350,000 between 1990 and 1999. U.S. Department of Labor data show that from
1999 to 2000 the numbers of utility employees working in power generation
dropped from 350,000 to 280,000, and in transmission and distribution from
196,000 to 156,000, while electricity consumption continued to increase. Among the consequences were drastic
reductions in training. At a FERC
Technical Conference in Philadelphia, one system operator observed, “We have
downsized quite a bit in our operating staff.... There is not a whole lot of
time left for training.”[23] Many systems had no operator training
programs, relying solely upon “on-the-job” experience. An independent European analysis has
concluded that personnel reductions played an important part in recent
blackouts there.
During the
past 15 years there have been major shifts in the qualifications, experience,
and knowledge required of those who control electric power policy and manageing
electric power activities.[24],
[25]
Past
experience has shown that technical standards and procedures are much less
important than the qualifications of the individuals who apply and enforce
those standards and procedures.
Nonetheless, in response to the new preeminence of market concerns,
appointments to key industry regulatory and reliability organizations have
increasingly downplayed technical knowledge and experience.[26] Many appointees to key electric energy
policy positions, such as FERC Commissioners, show a complete lack of the
experience relevant for their positions, or are beholden to certain segments of
the industry.[27]
Deregulation has led to a failure to transfer knowledge gained from past blackouts even though such knowledge could help prevent, or accelerate recovery from, future outages. This lack of knowledge transfer contributed to the 2003 blackout. We delineate the failure in knowledge transfer by reviewing investigations of past blackouts as well as the 2003 blackout.
Between
1965 and 1977 there were three major blackouts affecting the eastern U.S. In 1978 a major blackout shut down all of
France, an outage in scope close to the size of the August 14, 2003 blackout. Reviews of the 1965 northeastern U.S. and
1967 PJM blackouts led to the realization that extensive regional coordination of planning
and operations was required to improve reliability.
Other
lessons were learned from reviews of prior blackouts, e.g., the need to make
certain that relay settings and transmission ratings were consistent and
communicated to operating personnel (Northeast 1965), the need for “black
start” capability (Northeast 1965), the vital need for an Energy Management
System (EMS) to analyze potential problems (PJM 1967), the need for improved
system restoration procedures (Northeast 1965, PJM 1967, Con Edison 1977), the
need for adequate communication within and between control areas (Con Edison
1977), the need for adequate reactive supply (France 1978), and the need to
make certain that line clearances on rights of way are maintained (West Coast
1996).
Following
the blackouts mentioned above, many technical reports and papers were prepared,
presentations were made at various public and technical committee meetings, and
magazine and newspaper stories were published.
Some of the lessons were specifically addressed in reliability council
documents. However, these lessons have
been ignored by the new, post-deregulation policy makers in today’s electric
power industry. The DOE report on the
blackout identifies these failures to transfer lessons learned from past
blackouts as an important contributor to the August 2003 blackout.
The head of
the DOE’s Office of Transmission and Distribution[28]
commented that the restoration of power after the August 14th blackout in about
2½ days was a remarkable achievement.
This was a prime example of two of our observations: an especially
uninformed regulator and the failure to pass on past knowledge. Almost 40 years
earlier (November 1965), a system almost as large was completely restored in 13
hours. Following the blackout of all of
France in 1978, the entire system was restored in four hours! Understanding how and why these restorations
were accomplished is important knowledge, but was totally ignored by policy
makers after August 14, 2003 – even though a three-volume report on the 1965 blackout was
published by the U.S. government (one of this paper’s authors having served on the study
group) and a
report on the
1978 French Blackout (written by another of this paper’s authors on commission from the DOE).
The effect
of the lack of technical competence on reliability and the August 14th blackout
can be illustrated by a few examples:
1. FERC had approved the operation of the
Midwest Independent System Operator (MISO), stretching across all or parts of three
reliability councils. While FERC’s
purpose was to facilitate market procedures, no analysis of the technical
adequacy of MISO was attempted. There
was no appraisal of whether MISO was prepared to assume operating
responsibilities, whether the MISO control center was complete, and whether its
operators were properly trained or qualified.
In April 2003, MISO prepared its “Regional Transmission Organization
(RTO) Reliability Plan.” It was vital
that the procedures involved to coordinate MISO’s operations with existing
reliability councils and security coordinators be carefully reviewed. Quoting from the DOE Interim Blackout
Report:
• “Before approving
MISO, FERC had asked NERC for a formal assessment of whether reliability could
be maintained under the arrangements proposed by MSIO and PJM. NERC replied affirmatively but
provisionally. NERC conducted audits in
November and December of 2002 of the MISO and PJM reliability plans, and some
of the recommendations are still being addressed. The adequacy of the plans and whether the plans were being
implemented ads written are factors in NERC’s on-going investigation.”
Even though the plans had not been deemed adequate, FERC
approved the operation of MISO.
2. The chairman of FERC recently created a new
department to address reliability matters, and assume national control of
reliability standards and their enforcement.
Additional engineers were hired for this purpose. The new staffers will work in the Office of
Markets, Tariffs, and Rates, under the management of those responsible for
enhancing market procedures. The
creation of this department is a recognition of past FERC failures, but the
oversight of the department’s work by personnel whose focus is to enhance
markets demonstrates FERC’s inability to understand the problem.
3. The government’s blackout investigation is another example of the failure to allow technically competent advisors to contribute. The government carefully selected personnel and orchestrated the investigation’s limited content.[29] The government controlled the writing of the report, the public hearings, and workshops conducted after the blackout. Technically competent participants were given bare minimum opportunities to comment. The government even required those involved in the investigation to sign confidentiality agreements, an action unprecedented in the history of electric power in the U.S. By contrast, following the 1965 blackout, Joseph C. Swidler, then chairman of the Federal Power Commission (FERC’s predecessor), was instructed by President Lyndon Johnson to have the nation’s best engineering talent available to supervise the investigation – and that is exactly what happened.[30] The U.S.- Canada Power Outage Task Force and the Electric System Working Group for the August 2003 blackout were composed almost entirely of individuals either in federal or state regulatory positions. Few appear to have had any technical experience in planning or operating a power company. The NERC steering and working groups were staffed by highly qualified technical people; however, these participants did not oversee preparation of the study’s report which was a DOE staff effort.
Often essential knowledge is held by one individual or a very few teams and cannot be passed on except though direct contact, i.e., a “doctor-intern” type relationship. Programs that encouraged early retirement in electric power companies facilitated the departure of personnel with extensive experience causing a breakdown in the essential transfer of knowledge.[31] NERC’s approach of writing voluminous procedures is not sufficient to correct this problem. As we have noted, the best procedures are only as good as the experience and expertise of the parties applying them.
The stage
was set for the events of the 2003 blackout by changes in the structure of
the electric power industry.[32],
[33] The federal government, mostly through FERC,
had mandated untried and inappropriate structural changes. It established new rules and procedures that
facilitated bad behavior (e.g., Enron), with no analyses of the potential
effect on reliability.[34],
[35] In a survey, more than half of the utility
executives polled (along with many others) expressed the belief that industry
restructuring has caused a decline in reliability.[36] Only participants with no technical
background argued that market forces could somehow produce good engineering
designs and operations.
In the wake
of these failures, “spin” has, perhaps predictably, replaced substance, for
example:
Ø
NERC’s publication of the
so-called “Version 0” of its reliability standards was promoted to the press
and public as a direct response to the August 14, 2003 blackout – when, in
fact, it was nothing more than the restatement (in a somewhat different format)
of the same reliability standards NERC had been using for more than a decade.
Ø
NERC continues to deny that
changes proposed to its transfer capability definitions are in effect a
lowering, and watering down, of its standards.
Yet this is demonstrably so in the view of anyone familiar with the
subject.[37] Unless this
trend is reversed, more blackouts will happen.
The recently proposed Reliability
First Corp., which would merge the regional councils -- MAAC, ECAR,
Mid-Atlantic Interconnected Network (MAIN), and possibly Midwest Reliability
Organization (MRO) -- into a single new reliability council, is being presented
as a “fix” to some of the problems that led to the August 14, 2003 blackout. But this merger in
no way addresses the important question of the host of geo-electrically
small control areas in the midwest, which contributed significantly to the 2003
blackout. Had Reliability First Corp.,
as now proposed, been in existence on August. 14,
2003, nothing would have been different.
This is a solution searching for a problem, spin rather than substance.
The authors
have been asked to provide recommendations, a difficult assignment. In the massive effort to “deregulate” and
“restructure” the electric power industry, the Laws of Physics were ignored,
replaced by a blind conviction that the Laws of Economics could provide all
things – including a reliable system.
Unfortunately, this has been proven to be a tragic mistake. The problem with correction, however, is
that a fundamentalist market philosophy has so permeated the entire industry,
from the Federal Government and its regulatory officials to the industry’s own
organizations, that to undo the damage will likely take an effort well beyond a
few simple recommendations. The problem
cannot easily be fixed since the problem is an innate attitude or belief
system, not an error or two in procedures or protocols. An indication of this is the fact that,
despite such evidence as the California Meltdown, unprecedented price spikes,
the criminal actions of Enron and others, and the most devastating blackout in
our history, policy makers still steadfastly deny that deregulation and restructuring
had anything at all to do with any of it.
Sociologists call this “cognitive dissonance.”
Recognizing this difficulty, there are a number of steps
that could
be taken to
start the nation on its difficult corrective path:
Ø
Before approving any new ISO/RTOs, ensure and
demonstrate that the entity is fully functional.
Ø
Investigate and recommend
guidelines for the geo-electrical characteristics of control areas.
Ø
Require NERC to roll
back the reductions in reliability standards implemented since 1998.
Ø
Prohibit NERC from
implementing any further reductions in reliability standards.
Ø
Permit any state or reliability entity to
mandate more stringent reliability standards than NERC’s. In other words, make sure that NERC
standards are a floor, but not a ceiling.
Ø
Before implementing a new
market design,
ensure and demonstrate that the design’s impacts on the reliable operation of
the power system
have been fully evaluated.
Ø
To make markets work
more efficiently and effectively, emphasize in policy standards the need to foster cooperation
between organizations.
Ø
Develop standards for
technical qualifications required for key government and industry positions, including those responsible
for establishing electric power policies, and for management, design,
and operation of the transmission grid.
Ø
Require that appointments to
FERC and the new DOE Office of Electricity of Delivery and Energy Reliability, and to the
NERC Board and senior management positions, have demonstrated expertise and experience
in electric power and are vetted by the National Academy of Engineers, with
input from the Institute of Electrical and Electronic Engineers (IEEE), Edison
Electric Institute (EEI), the American Public Power Association (APPA),
and National Rural Electric Cooperative Association (NRECA).
Ø
Mandate that DOE, in
consultation with FERC, NARUC, and NERC, undertake a biannual “National Power
Survey” modeled after the 1964 survey.
This survey should give emphasis to reliability risks, including such
incidents as the loss of major gas pipelines, as well as economic constraints.[39]
Ø
Investigate and develop new
programs for encouraging and improving the transfer of technical experience and expertise
in the electric power industry and universities; such efforts could be enhanced by utilizing
experienced retired engineers from the electric power industry.
Ø
Investigate the effects that extensive
labor reductions have had on overall national reliability, and on the ability
to cope with national disasters and acts of terrorism.
Ø
Require that marketing areas
and reliability council areas be consistent.
Ø
Support the reporting and
exchanging of information related to system reliability. (Concerns exist about the consistency of
some information,
--and the
availability of data to the entire electric power industry.) The Federal Government could play an
important role in enhancing the definition, collection, and
sharing of information.
Ø
When adjusting generation
because of transmission economic constraints, insure that such adjustments
minimize reliability risks.
Ø
Investigate and monitor
reductions of maintenance expenditures as indicated in reports to FERC as a
part of FERC’s reliability monitoring function.
Additional references can be
obtained at the following web sites:
[1] DOE personnel have indicated in correspondence with the authors they had more important things to look into. Kevin Kolevar, March 8, 2005, attachments to letter to J.A. Casazza (see pages 12 and 13).
[2] The Congressional Research Service Report to Congress on Electric Utility Reform update of April 21, 2005 does not discuss such issues as industry behavior and its impact on reliability.
[3] Casazza, John A., 1993, “The Development of Electric Power Transmission”, originally published by the Institute of the Electrical and Electronic Engineers. Now available from www.Lulu.com.
[4] Rosen, Richard A, 2003, “The August 14, 2003 Blackout in the United States: Technical and Regulatory Issues”, Report to the Swiss Federal Office of Energy, November 11 (Tellus Institute, r.rosen@tellus.org).
[5] In Con Edison, this resulted in disassembling the Planning organization that had reported to one Vice President into three entities reporting to three different Vice Presidents. In AEP, the System Planning Department, which had reported to the Chief Executive Officer for many years, was disbanded and its functions were assigned to different organizations and eventually eliminated.
[6] Delea, F., and J. Casazza 2005, “Why Have Lessons Learned Not Been Transferred to the Current Generation of Power System Engineers, Managers and Policy Makers and What Can Be Done About It?”, IEEE Power Engineering Society, San Francisco, June (also Energy Pulse, October, 2004).
[7] In the United States, reductions in personnel have been greater in the deregulated portions of the industry than in those still under regulation. Although some reductions in labor force are appropriate at times, others are the result of a focus on immediate profits and contributed to the blackout. A competent analysis of the effects of such labor reductions has been provided by the International Brotherhood of Electrical Workers (IBEW) and the Utility Workers Union of America (UWUA). See James L. Hunter, Jan. 20, 2000, Submission to U.S. Department of Energy Power Outage Study Team (POST), January 20, 2000, Jack McNally, Submission to U.S. Department of Energy Power Outage Study Team (POST).
[8] U.S. Dept. of Labor, Bureau of Labor Statistics, www.bls.gov.
[9] Neederjohn, M. Scott, 2003, “Regulatory Reform and Labor Outcomes in the U.S. Electricity Sector”, Monthly Labor Review, May.
[10] Hunter, James H., 2000 “ Initial Comments of IBEW Local 1900” U.S. Department of Energy Power Outage Study Team (POST), January 20.
[11] Ownership and control of the transmission assets of the subsidiary electric utilities of First Energy were transferred to American Transmission Systems (ATSI), a subsidiary of First Energy and the first electric transmission subsidiary of an investor-owned utility in the U.S. Effective October 1, 2003, ATSI became part of the Midwest ISO through GridAmerica (a subsidiary of National Grid). GridAmerica is an independent transmission company within the Midwest ISO. With this transaction, ATSI’s control of those functions and activities were to be performed by the Midwest ISO and GridAmerica.
[12] See page
20, in Rosen (2003) (footnote 4, above) concerning excessive numbers of trades.
[13] “About Us” on the NYISO web site www.nyiso.com, 2004 Annual Report.
[14] PJM web site www.PJM.com.
[15] ISO New England web site www.iso-ne.com.
[16] Richard, Alan H. 2004, “The Right Question”, Public Power, March-April.
[17] This material is part of, but by no means all, of the material covered in Chapter 3 of the April 2004 Blackout Report.
[18] “The Development of Electric Power Transmission - The Role Played by Technology, Institutions, and People,” 1993 IEEE Press. Now available from www.lulu.com.
[19] This is evidenced by August 14, 2003 recordings of discussions between system operators, who wished to reduce power transfers, and marketers, who saw this as a threat to their profitability.
[20] “Keeping the Power Flowing”, 2005, Consumer Energy Council of America, Jan. (Fig. 6, p. 33).
[21] Hunter, James J., 2000, “Initial Comments of IBEW Local 1900” U.S. Department of Energy Power Outage Study Team (POST), Jan 20.
[22] “Keep the Power Flowing”, 2005 Consumer Energy Council of America, January (Fig. 3, p. 28).
[23] Transcript-Panel 1, DOE Technical Conference on Blackout, Comments by Scott Moore, Philadelphia, Dec. 1, 2003.
[24]Over the years the experience of the majority of the industry executives has shifted from the technical to the financial and political. This is evidenced by changes in the membership on the Edison Electric Institute Board of Directors.
[25] The control of NERC has shifted over the past 15 years from those with technical backgrounds to stakeholders, most of whom have financial or political backgrounds. This is evidenced by changes in the NERC Board of Trustees.
[26] Florman, Samuel C., 1976, “The Existential Pleasures of Engineering”, St. Martin’s Press.
[27] Barranco, Miriam, 2005, “Should There Be Reform for the Government Appointment Process?” Appendix B, www.PEST-03.org, Publications, “Blackouts and Blunders”-January 21.
[28] Recently changed to Office of Electricity Delivery and Energy Reliability.
[29] Smith, Rebecca, 2003, “Political Agenda May Detract From Clear Blackout Analysis”, Wall Street Journal, August 21.
[30] “Power and the Public Interest-The Memoirs of Joseph C. Swidler”, 2002, The University of Tennessee Press, pp. 156-160.
[31] Hyklo, Jim, 2005, “Thanks for the Memories: Capturing Expert Knowledge”, Power, May.
[32] DOE POST study, IBEW testimony.
[33] Casazza, J.A., 1998, “Blackouts: Is the Risk Increasing?” Electrical World, April.
[34] Whightman, Donald, 2005, “President’s Message” LIGHT, April.
[35] Lerner, Eric J. 2004, “What’s Wrong with the Electric Grid?” The Industrial Physicist, Oct.
[36] Gale, Roger (G.F. Energy) 2004, “2004 Electric Outlook” (Bloomberg News , Jan 13).
[37] Specific examples are past revisions of the 10- and 30-minute reserve requirement to 15 and 105 minutes, and proposed revisions to NERC Standard 600 to eliminate provision for the loss of both circuits on a double-circuit tower line.
[38] These recommendations were prepared prior to recent Congressional action that made making reliability standards mandatory. They have since been reviewed and remain unchanged, since the problem is not whether the process is mandatory, but how strong the standards are, how our recommendations are implemented, and how competent those implementing them are. In any case, since the Energy Policy Act of 2005 does not address the underlying causes of the 2003 blackout, it will have no effect in improving the reliability of the bulk power system.
[39] “It’s Time to Challenge Conventional Wisdom”, Harrison Clark, Transmission and Distribution World, Oct 2004.